Well 5 Construction

  1. Well 5: 07/12/19 Weekly Project Update

    The drilling contractor has installed the drilling pad matting and silt fencing. Construction fencing is anticipated on Tuesday, July 16. Read on...
  2. Well 5: Tree Removals Anticipated to Occur Between June 24th and July 8th

    The removal of four trees located inside the construction area is anticipated to occur within the next two weeks. Read on...
  3. Well 5: Installation of Transmission Main Tentatively Scheduled to Begin July 8th

    Installation of the Transmission Main for the well #5 construction project is tentatively scheduled to begin on July 8th. Construction is anticipated to take approximately three weeks. Read on...

Overview

The Village is implementing a water infrastructure improvement plan, utilizing a low interest loan from the IEPA's revolving loan program. The construction of a new deep well for the Village's water supply has been approved by the Village Board and is scheduled for construction in 2019. The Village has secured funds for the construction of the well through the IEPA. 

Construction Updates & "Notify Me"

One of the most important aspects of a successful roadway project is communication with residents. Construction updates will be posted in the "News Flash" section on the right side of this page. These updates will contain information pertaining to the construction schedule, anticipated changes to the project and any additional progress updates. 

To sign up to receive weekly updates in an e-mail and/or text message, follow the steps below.

  1. Click on "Stay Informed" on the left side of this page.
  2. Enter your e-mail address in the text box at the top of the page and click "Sign In".
  3. Scroll down to the "News Flash" section of the page and click the Email address next to "Well No 5 Construction".
  4. Optional: If you would like to also receive text message updates, first select the check box below your e-mail next to "I would like to be able to receive text messages on my mobile phone". Then click the Subscribe via text messaging next to Road Construction Projects.


  1. Sanitary Main
  2. Well Drilling
  3. Transmission Main
  4. Pumping Equipment

The project will begin late fall, early winter of 2018 with the replacement of approximately 100' of sanitary main running north-south through Field Park. The sanitary main adjacent to the proposed well site will be upgraded to potable water quality pipe.