Posted on: August 16, 2017

2017 Roadway Program - West Lane Update

The contractor elected to begin work on Howard Avenue yesterday instead of Harvey Avenue. This decision was due to some private work being done in the area of Harvey Avenue that would have made access difficult for both parties. The contractor is planning...

Read on...

Road Construction Projects
Posted on: August 14, 2017

2017 Roadway Program - East Lane Open/West Lane Start Date

Howard/Harvey East Lane Opening

The east lanes and driveway aprons on Harvey and Howard Avenue are now reopened for public use. Please be cautious while driving on the east lanes as there are elevation changes between the east and west sides of th...

Read on...

Road Construction Projects
Posted on: August 9, 2017

2017 Roadway Program - Fair Elms Start Date/Harvey & Howard Update

Fair Elms Avenue Concrete Rehabilitation Start Date

The contractor is planning to begin the concrete patching project on the east lane of Fair Elms Avenue between 53rd Street and the cul-de-sac on August 11th, weather permitting. The west lane of Fair Elms...

Read on...

Road Construction Projects
Posted on: August 8, 2017

2017 Roadway Program - East Lane Updates

The contractor is tentatively planning on re-opening the east lanes of Howard and Harvey in the next few day. Please refrain from driving on the new pavement or driveway aprons until the barricades and construction tape has been removed by the contractor....

Read on...

Road Construction Projects
Posted on: August 8, 2017

2017 Roadway Program - East Lane Updates

The contractor is tentatively planning on re-opening the east lanes of Howard and Harvey in the next few day. Please refrain from driving on the new pavement or driveway aprons until the barricades and construction tape has been removed by the contractor....

Read on...

Road Construction Projects
Posted on: August 3, 2017

2017 Roadway Program - East Lane Concrete Pour

East Lane Completion

The contractor is scheduled to begin pouring concrete at Harvey Avenue and 39th Street tomorrow, August 4th, weather permitting. They will move to Howard Avenue once they complete Harvey. The contractor has been allowed to begin work a...

Read on...

Road Construction Projects
Posted on: July 25, 2017

2017 Roadway Program - East Lane Removal of Howard Avenue Begins Thursday

GM Cement is currently completing the removal of Harvey Avenue and is anticipated to begin removals on Howard Avenue Thursday, July 27, 2017 weather permitting. 

Residents should  have their vehicles out of their driveways by 7:00 am on T...

Read on...

Road Construction Projects
Posted on: July 18, 2017

2017 Roadway Program - Official Start Date

Official Start Date

The official start date for the roadway portion of the project will begin on July 20, 2017, at 7:30 AM, weather permitting. Bad weather will result in a delay to the start date until the next available working day.  The contrac...

Read on...

Road Construction Projects
Posted on: July 14, 2017

2017 Roadway Program - Construction Update and Temporary Change in Contact Info

Construction Update

The storms earlier this week delayed the contractor from beginning the saw cutting and excavation of the east lane of Howard and Harvey Avenue. We require at least 24 hours of notice from the contractor before excavation work can begin ...

Read on...

Road Construction Projects
Posted on: July 7, 2017

2017 Roadway Program - East Lane Construction Start Date Reminder

G&M Cement is planning to begin construction of the east lanes of Harvey and Howard during the middle next week, weather permitting.   A construction update will be sent out at least 24 hours ahead of time so please continue to check your e-m...

Read on...

Road Construction Projects
Posted on: June 23, 2017

2017 Roadway Program - Construction Update and Golf Cart Information

Construction Progress Update

The underground contractor has completed all sewer work included in Phase 1 of the project.  Phase 2, the reconstruction of the east lane of both Howard and Harvey, has been delayed until the week of July 10, 2017. &am...

Read on...

Road Construction Projects
Posted on: June 13, 2017

2017 Roadway Program - Sewer Installation Update

Construction Update

The contractor has completed the major sewer work on the 4000 block of Harvey Avenue.  They will continue north today to work on various sanitary and drainage structures.  Residents of Howard Avenue (47th-48th) should ...

Read on...

Road Construction Projects
Posted on: May 22, 2017

2017 Roadway Program - Official Schedule and Updates

Project Schedule

The official project schedule has been received from G&M Cement.  The schedule may change due to weather or unforeseen circumstances during construction.  The schedule is as follow:

May 30th - June 16th: All sewer work...

Read on...